Starting Duration Tests
Open Grid view -> Site-> Duration test schedules. Right-click on the test group row you wish to start a duration test for. Select "Start duration test" from the right-click menu.
Starting Extended Duration Tests
Open Grid view -> Site -> Duration test schedules. Right-click on the test group row you wish to start a duration test for. Select "Start extended duration test" from the right-click menu.
Starting Function Tests
Open Grid view -> Site-> Function test schedules. Right-click on the test group row you wish to start a duration test for. Select " Start function test" from the right-click menu.
All types of tests can also be started by right-clicking on a particular test group in the Grid view -> Site -> Test groups view.